8 Construction Procedure Stages of Water Bound Macadam (W.B.M) Road

8 Construction Procedure of W.B.M Road

The construction of a W.B.M road is carried out in the following stages:
Construction Procedure Stages of  Water Bound Macadam

1. Preparation of The Foundation

The foundation for receiving the new layer of W.B.M may be either the sub grade or sub-base course.This foundation layer is prepared to the required grade and camber and the dust and other loose materials are cleaned. 
On existing road surface ,the depression & pot holes are filled and the corrugations are removed.

2. Provision of Lateral Confinement

This can be done constructing the shoulders to a thickness equal to that of the compacted W.B.M layer and trimming the inner sides vertically.

3. Spreading of Coarse Aggregates

The coarse aggregates are spread uniformly to the proper profile and even thickness up on the prepared foundation and checked by templates.

4. Rolling 

After spreading the coarse aggregates properly, compaction is done by three wheeled power roller (6 to 10 tones) or equivalent vibrating roller .

The Rolling is started from the edges and progressed gradually towards the centre of rod road until adequate compaction is achieved .
On super-elevated portion, rolling it started from the inner or lower edge and progressed gradually towards the outer or upper edge of the pavement.

5. Application of Screenings

After the coarse aggregates are rolled adequately the dry screenings are applied gradually over the surface and try rolling is continued as the screenings are being spread. Brooming operation is also carried out simultaneously.

6. Sprinkling and Grouting 

After the application of screenings, the surface is Sprinkled with water ,swept and rolled.

7. Application of Binding Material

After the application of screenings and rolling, binding materials is applied at uniform and slow rate at two or more successive thin layers.After each application of binding material ,the surface is Sprinkled with water and wet slurry swept with brooms to fill the voids.

8. Setting & Drying  

After final compaction, the W.B.M course is allowed to set over night.On the next day the Hungry spots are filled with screenings or binding materials,lightly sprinkled with water if necessary and rolled. No traffic is allowed till the W.B.M layers sets and dries out.